Minimizing Makespan in a Two-Machine Flowshop with Dynamic Arrivals Allowed

Cited 43 time in webofscience Cited 0 time in scopus
  • Hit : 409
  • Download : 0
This paper considers a scheduling problem for a two-machine flowshop where a discrete processing machine is followed by a batch processing machine and a finite number of jobs arrive dynamically at the first machine. In the flowshop, the discrete processing machine processes one job at a time and the batch processing machine processes a batch of jobs simultaneously. The objective is to find the optimal schedule which minimizes the maximum completion time (makespan) of all jobs. In the situation where preemption is allowed on the discrete processing machine, it is shown that the optimal schedule can be found in polynomial time. However, in the situation where no preemption is allowed on the discrete processing machine, it is shown that the problem is NP-complete, for which an efficient heuristic solution algorithm is constructed and its tight worst-case error bound is derived. Numerical experiments show that the heuristic algorithm consistently generates good schedules.
Publisher
Pergamon Press Ltd.
Issue Date
2002-02
Language
ENG
Article Type
Article
Keywords

BATCH PROCESSING MACHINE; INCOMPATIBLE JOB FAMILIES; TOTAL COMPLETION-TIME; BURN-IN OPERATIONS; ALGORITHMS

Citation

COMPUTERS AND OPERATIONS RESEARCH, v.29, no.3, pp.275 - 294

ISSN
0305-0548
URI
http://hdl.handle.net/10203/80608
Appears in Collection
IE-Journal Papers(저널논문)
Files in This Item
There are no files associated with this item.
This item is cited by other documents in WoS
⊙ Detail Information in WoSⓡ Click to see webofscience_button
⊙ Cited 43 items in WoS Click to see citing articles in records_button

qr_code

  • mendeley

    citeulike


rss_1.0 rss_2.0 atom_1.0